NAHA Port Public International Container Terminal Project
Schedule through commencement of this Project
|
|
|
 |
|
|
|
|
The schedule through the commencement of this Project is planned as follows:
|
|
|
 |
Public Notice for RFP |
November 24, 2004 |
 |
Issuance of RFP |
November 24 - December 7, 2004 |
 |
Start of submission of proposals |
November 24, 2004 |
 |
Deadline for submission of proposals |
December 7, 2004 |
 |
Public disclosure of proposals |
December 9 - December 16, 2004 |
 |
Selection of the private enterprise as the Operator |
December 21, 2004 |
 |
Authorization of the private enterprise as the Operator |
December 22, 2004 |
 |
Public disclosure of the Authorized Operator |
December 22, 2004 |
 |
Signing of Basic Agreement |
January 24, 2005 |
 |
Application for Special Zones for Structural Reform |
January 2005 |
 |
Signing of Lease Agreement |
May 12, 2005 |
 |
Commencement of operations |
January 1, 2006 |
|
|
|
|
|
|